Replacement of Burdon Canal Bridge Begins on George Price Highway
posted (November 24, 2026)
And another major part of the George Price Highway Upgrading Project is the replacement of the Burdon Canal Bridge, which started today. This will add to the traffic delays now being experienced on the George Price Highway:

Evondale Moody, Chief Engineer
"I think about a month ago, I sent out a notice informing the public that we will be closing the Burton Canal Bridge come January. All right. I sent that notice because vehicular traffic, especially heavy trucks and heavy goods vehicle, will need to use the Chetumal Street, Philip Goldson Highway, John Smith Road come January. Reason being is that we have to replace Burton Canal Bridge. And so what the contractor is doing at this point in time is the removal of the old deck for the old Burton Canal Bridge, because that is where we're going to build a temporary bridge that will be used during the construction period for the new Burton Canal Bridge. So he has commenced those works with the removal of the old deck that requires some close-some intermittent closure of the highway-because the crane has to be working from the existing bridge as we speak, because it's difficult for us to work off the road because of the high-tension wires that are there. We have consulted with BEL because we have to move at least six poles that are there, including the overhead high-tension wires, for us to accommodate the construction of the new bridge, but that has not been done as yet. And so in anticipation of those works, the contractor has commenced with the removal of the old bridge itself. And that is creating some delays in terms of the traffic because we have to have the crane working online on the existing road to remove that deck. That is correct."

Jaleeza Roberts:
"Okay. And how long is this expected to take place, this one specifically?"

Evondale Moody, Chief Engineer
"Until January."

Jaleeza Roberts:
"Okay, so from now until January."

Evondale Moody, Chief Engineer
"Yes, it's off and on. And so once we remove the deck, the idea is that we're going to build a new deck using the two existing abutments for that wall structure, because the team has assessed that existing bridge structure and found out that the two abutments are still intact, and so what we're doing is remove the old deck, replace it with new girders to construct a new deck on that bridge, and then we'll place a new wooden deck on top. And that will be the diversion for the next year passing Burton Canal while we demolish the existing bridge come January. And so we have to put that in place so that we could accommodate light vehicles and buses to traverse that area over the next year."