7 News Belize

Jilted Contractors Dismissed in Supreme Court
posted (July 21, 2009)

The National Stadium looks like a national disaster area, but at least government has successfully resisted a lawsuit brought by the jilted contractor for $2.5 million. Yesterday the claim for breach of contract brought by Bella Vista Development Company Ltd. and Lopez Equipment Ltd. Owned by Javier Berbey and Wilhelm Lopez against the Government of Belize was dismissed by Supreme Court Justice Oswell Legal.

The claim arose out of a contract signed by in December of 2007 for the construction of the Belize Sports Center at the Marion Jones Complex on Princess Margaret Drive. The contract was signed a mere 2 months before the general elections, and the government terminated it only 3 months later in March of 2008.

The companies argued unsuccessfully that they would have derived a profit of $2.5 million, 15% of the $16 million contract. Justice Legall also dismissed the government’s counterclaim against the contractors for repayment of money that was allegedly disbursed to them as an advance to initiate the project. The claimants were represented by Godfrey Smith, while the Government was represented by Crown Council, Phillip Palacio.

Home | Archives | Downloads/Podcasts | Advertise | Contact Us

7 News Belize