Moe’s Pizza By The Sea Moving For A January Opening
posted (November 13, 2018)
Construction resumed last week on Moe's Pizza on the Sandlighter's Promenade. This is after a stop order from the Department of the Environment halted work for three weeks. As we understand it, the Department of the Environment has instructed the developer Haisam Diab to do basically what any builder would do: contract with Waste Control for garbage disposal, hook up to the sewer mains, and pipe all grey water into the sewer mains. The DOE also assessed developer Hiasam Diab with a $500.00 monitoring fee.

Diab is planning for a mid - January opening.

The project generated some political scrutiny when it was thought that the City Council had sold Diab the land. It is actually a lease - where the council will own the building at the end of the lease.